The Appellate Tribunal for Electricity has dismissed an appeal filed by the Tamil Nadu Electricity Board (TNEB) against an order of the Tamil Nadu Electricity Regulatory Commission on payment of dues to GMR Power Corporation Ltd under a power purchase agreement.

GMR Power Corporation Limited (GPCL), a subsidiary of GMR Infrastructure Limited (GIL), had approached the Tamil Nadu Electricity Regulatory Commission (TNERC) for adjudication of disputes with Tamil Nadu Electricity Board (TNEB) arising out of the power purchase agreement with TNEB.

TNERC, by its order dated 16 April 2010, had allowed the claims of GPCL and directed TNEB to pay approximately Rs480 crore with interest in six equal monthly installments to the aggrieved.

TNEB then moved an appeal before the Appellate Tribunal for Electricity (APTEL). However, APTEL, by its judgment dated 28 February 2012, dismissed the appeal and upheld the order of TNERC.

While accepting the appeal, APTEL had, in an interim order, on 19 November 2010, asked TNEB to clear the dues to GPCL.

GPCL can now retain the amount of Rs537 crore (including interest) received till date from TNEB by virtue of the interim order in settlement of the dues from TNEB.

The APTEL order has also adjudicated on an interlocutory application filed by TNEB, wherein APTEL has directed that the interest to be computed on the amount of fuel invoices payable by GPCL to Hindustan Power Corporation Limited for credit periods should be paid or set-off against payments due to GPCL from TNEB. 
 


 

Latest articles

Lohum starts Zimbabwe lithium operations with first ore shipment

Lohum starts Zimbabwe lithium operations with first ore shipment

OpenAI deepens Samsung alliance on next-generation AI chips

OpenAI deepens Samsung alliance on next-generation AI chips

Google commits €13 billion to Finnish AI infrastructure with nuclear deal

Google commits €13 billion to Finnish AI infrastructure with nuclear deal

Texas audits 474 GW data centre queue as US tackles speculative power demand

Texas audits 474 GW data centre queue as US tackles speculative power demand

China issues overseas competition guidelines for automakers as exports expand

China issues overseas competition guidelines for automakers as exports expand

Private investment strengthens as India records 7.8% GDP growth in Q1

Private investment strengthens as India records 7.8% GDP growth in Q1

Switzerland keeps October 1 transparency register launch despite hack fears

Switzerland keeps October 1 transparency register launch despite hack fears

US 10-year yield tests 4.75% as hawkish Fed signals lift rate bets

US 10-year yield tests 4.75% as hawkish Fed signals lift rate bets

EPA weighs refinery waivers of up to 1.8 billion RINs amid farm backlash

EPA weighs refinery waivers of up to 1.8 billion RINs amid farm backlash
View details about the software product Informachine File Manager
View details about the software product Informachine News Trackers