National
Thermal Power Corporation Ltd.(NTPC) and Bhabha Atomic
Research Centre (BARCwill undertake collaborative research
to develop and deliver automated boiler tube inspection
system for coal-based thermal power plants.
This
is a project to develop a prototype crawler for automated
boiler tube inspection in coal-based power stations. NTPC
Ltd. will supply inspection probes. BARC will develop
the technology and assemble the prototype automated boiler
tube inspection system in their robotic lab at BARC. The
prototype will be tested in one of the NTPC power stations.
Preliminary
estimated cost of this collaboration research project
is Rs170 lakh and the total time envisaged for completion
of this project is 26 months. Power minister Sushilkumar
Shinde said this in a written reply in Lok Sabha today.
|